Track every shop drawing until it is approved.
Build a free construction submittal log with spec sections, shop drawings, status tracking, overdue board, review-cycle days, audit checks, and CSV or print export. No signup.
- Client-side & private
- No signup
- Overdue board
- Print & CSV export
1. Project & GC header
Identify the job site, general contractor, architect/engineer, and current log date to drive overdue math.
2. Submittal register
Add, manage, and audit shop drawings, product data, material samples, and mix designs.
How the Construction Submittal Log Works
A construction submittal log serves as the master tracking index for all shop drawings, material samples, product data sheets, mix designs, and calculations required under contract specifications (CSI MasterFormat). Before a subcontractor can fabricate structural steel, pour concrete, or install commercial HVAC units, the specified materials must be reviewed and approved by the architect and engineer of record.
This builder calculates review turnaround times, highlights overdue items past their required on-site date, and generates clean, professional registers for owner-architect-contractor (OAC) progress meetings.
Submittal Statuses & Overdue Logic Rules
Keeping an accurate submittal register requires explicit status definitions. This tool evaluates each item's status against the log date and required dates using standardized construction management logic:
| Status | Open / Closed State | Overdue & Review Logic |
|---|---|---|
| Draft | Open | In internal preparation by sub/GC; not yet transmitted to reviewer. |
| Submitted | Open | Transmitted to General Contractor or A/E team; awaiting review startup. |
| Under review | Open | Active review by Architect/Engineer. Overdue if Required Date < Log Date. |
| Approved | Closed / Resolved | Fully approved. Fabrication and site delivery may proceed as submitted. |
| Approved as noted | Closed / Resolved | Approved subject to contractor incorporating specific marked notes; no resubmission needed. |
| Revise and resubmit | Open | Rejected in current form due to spec deviations or missing details; requires corrected resubmission. |
| Rejected | Open / Action required | Unacceptable submission. Must submit alternate product or design package. |
| Closed | Closed / Resolved | Administratively closed or superseded by alternate submittal package. |
CSI Spec Section, Submittal Type, and Revision Discipline
Structured spec section numbering prevents lost submittals and costly field rework. Construction teams maintain discipline by adhering to standard workflows:
- CSI MasterFormat Spec Sections: Always group items by standard 6-digit CSI division numbers (e.g.
03 3000Cast-in-Place Concrete,05 1200Structural Steel Framing,09 9100Painting). - Submittal Types: Categorize items accurately—Shop Drawings require technical engineering review, Product Data requires catalog specification verification, and Samples require visual/finish sign-off.
- Revision Tracking: Start initial submissions at Revision
0. When an item receives a Revise and Resubmit stamp, increment the resubmission to Revision1(or0A) to preserve the historical audit trail. - Lead Time Planning: Track vendor lead times (in calendar days) to calculate when shop drawings must be submitted to prevent delaying the site critical path.
Walkthrough: Harbor Ridge Commercial Buildout Example
Consider a commercial tenant improvement project—Harbor Ridge TI (#HR-TI-2026) managed by Northline Builders LLC:
- SUB-001 (03 3000 Concrete Mix Design): Submitted 21 days ago, reviewed in 7 days, and returned as Approved. Cast-in-place slab pour proceeds on schedule.
- SUB-008 (05 1200 Structural Steel Drawings): Submitted 10 days ago by Apex Ironworks. Flagged as OVERDUE because the required on-site date was yesterday and the structural engineer review remains pending.
- SUB-014 (09 9100 Interior Paint Product Data): Currently Submitted and undergoing routine review prior to its required date in 5 days.
- SUB-019 (08 7100 Door Hardware Schedule): Returned as Revise and resubmit due to a lockset finish mismatch (US26D specified vs US32D submitted).
- SUB-022 (23 0500 HVAC Cut Sheets): Marked as Draft / Critical priority to highlight long-lead rooftop unit procurement.
- SUB-027 (26 5100 Light Fixtures): Returned as Approved as noted with minor ballast model substitutions.
Operational & Contractual Limitations
This submittal log builder provides a fast, transparent client-side interface for daily site tracking and meeting preparation. However, contractors must note important operational boundaries:
Disclaimer: This tool is intended for internal tracking, progress reporting, and workflow organization. It does not replace the official system of record, contractual notice periods, or legal submittal review procedures mandated by AIA or EJCDC contract documents. Always verify submittal approvals directly against stamped contract drawings.
Frequently Asked Questions (FAQs)
- What is a construction submittal log?
- A construction submittal log is a master register used by general contractors, subcontractors, and project managers to track shop drawings, product data, material samples, and mix designs submitted to architects and engineers for approval before installation.
- How is submittal overdue status calculated?
- A submittal is flagged as overdue when its status is open (not Approved, Approved as noted, or Closed) and its required date is prior to the current log date.
- What is the difference between "Approved" and "Approved as Noted"?
- "Approved" means the submittal complies fully with specifications without changes. "Approved as Noted" permits fabrication or installation to proceed provided the contractor incorporates specific minor markups or comments written by the architect or engineer on the returned drawings.
- Can I export this submittal log to CSV or print it for site meetings?
- Yes. The tool provides instant CSV download for spreadsheets, formatted text copy, and a print-ready stylesheet optimized for physical submittal logs and O&M closeout binders without signing up.